The Old Forge, Warton

4 bedroom Luxury Home

Social housing decarbonisation, EWIS (UK) Ltd

Project management consultancy scheme

Chester road, Kidderminster

161 bedroom apartments

The Old Forge, Austrey

Pre-construction: 25 weeks             Construction: 48 weeks              Council: North Warwickshire
Scheme Detail: Design and Build of a 4 Bedroom Luxury home. Includes securing planning permission, executing the development by transforming it into a residential complex while preserving essential historical structures. Hunter Kavell managed the entire proposal from the scheme's initiation to final build, liaising with local authorities, conducting the design process and securing the necessary planning permission.

Social housing decarbonisation, EWIS (UK) Ltd

Pre-construction: 8 weeks             Construction: 12 weeks              Council: Barnsley Metropolitan Council/Berneslai Homes             Client: EWIS (UK) Ltd                                                                                                          Scheme Detail: A project management consultancy scheme where Hunter Kavell secured the scheme through a two-stage tendering process and delivered it by appointing the compliant subcontractors. The scheme consisted of carrying out the full retrofit works to 46 properties which consisted of a range of works including the following: 

  • External Wall Insulation

  • Internal Wall Insulation

  • Solar Panels

  • Boiler Replacements

  • Loft Insulation

  • PAS2030 Ventilation

  • Air Source Heat Pumps

  • Room in the Roof

  • Pitch Roof Insulation

  • Asbestos Removal

  • Scaffolding

  • Enabling

 

Subcontractors were selected through a vigorous comparison not just comparing the most cost effective, but the contractor who will bring the most value to the end users with factoring in time, cost and quality of works. The whole life costings for the client for best value for money was also considered.

Chester Road, Kidderminster

Pre-construction: 12 weeks             Construction: 35 weeks              Council: Wyre Forest District Council

Scheme detail: Design and build of an existing structure into 16 luxurious studio apartments, complete with both internal and external communal spaces. This included obtaining planning permission and securing necessary approvals required for build. Beyond the interior, the project extended its scope to the external surroundings. This included the installation of aesthetically pleasing block paving, the creation of soft landscaping features and the development of an entertainment room. These external amenities enhance the overall appeal and functionality of the residential complex, contributing to a holistic living experience for the future occupants. 